Community News - providing readers with the very latest in local news, sport, entertainment and more.
Camera IconCommunity News - providing readers with the very latest in local news, sport, entertainment and more. Credit: Community News

Road closures with road works starting on Mandurah Road tomorrow

Vanessa SchmittWeekend Kwinana Courier

THE southbound lane of Mandurah Road between Fifty Road and Tincombe Grove will be closed to traffic from April 12 to about May 19 while the approach to and exit from Safety Bay Road roundabout is upgraded to accommodate two lanes of traffic.

During construction motorists are encouraged to seek alternate southbound routes, such as Ennis Avenue or Baldivis Road.

Northbound traffic on Mandurah Road through the worksite will not be affected. However, motorists should approach with caution and observe traffic management directions.

PerthNow Digital Edition.
Your local paper, whenever you want it.

Get in front of tomorrow's news for FREE

Journalism for the curious Australian across politics, business, culture and opinion.

READ NOW

The works will be undertaken in two parts; with the approach lanes north of the roundabout constructed first followed by the construction of the exit lanes south of the roundabout.

The construction of the approach lanes north of the roundabout is scheduled to commence on Tuesday, April 12 and will take about three weeks to complete.

The southbound lane of Mandurah Road between Fifty Road and Safety Bay Road will be closed to traffic during this time and a detour will be in place along Fifty Road/Eighty Road/Safety Bay Road (as shown on Detour Map 1).

Once these works are complete, the southbound lane will be re-opened to traffic under appropriate traffic management.

Following completion of the approach lanes north of the roundabout, construction of the exit lanes south of the roundabout will commence (about Monday, May 2) and will also take about three weeks to complete.

The southbound lane of Mandurah Road between Safety Bay Road and Tincombe Grove will be closed to traffic during this time and a detour will be in place along Safety Bay Road/Eighty Road/Pike Road. Once these works are complete, the southbound lane will be re-opened to traffic under appropriate traffic management.

The required road closures have been scheduled so that Detour 1 (between Fifty Road and Safety Bay Road) occurs mainly during the upcoming school holidays to reduce the impact on Baldivis Primary School due to additional traffic on Fifty Road.

The scheduling of the road closures also take into consideration other works currently underway on Safety Bay Road between Eighty Road and Nairn Drive.

Resident enquiries can be directed to construction engineer Darren Dropulich on 9528 8511.